4 Steps to Prepare for an Asphalt Plant Controls Upgrade
BY Mike Raasch
4 Steps to prepare to upgrade the asphalt batch plant’s controls system
As indicated in the batch plant article series, upgrading the controls for an older facility normally requires more than replacing the wiring. Even if a hot mix asphalt (HMA) batch plant’s mechanical components have useful life remaining in them and you feel confident in your parts suppliers, the controls and electrical components may have become obsolete. When it’s time to modernize the control system, it’s time to assess the platform around the controls as well to improve reliability, diagnostics and operator interface. This starts with planning and doesn’t have to involve a large financial outlay.
Step 1. Document what you have.
Walk the plant with an electrician and operator who know the system best and inventory the control system together. Determine what PLC or relay logic is running the plant, which components are obsolete or unsupported, and what the drawings say versus what’s really in the panel. Most legacy plants have years of undocumented changes and surfacing those before a project starts is the single best way to avoid surprises mid-installation.
Step 2. Determine your objectives.
Define the reason for the upgrade and establish the project scope. The priority may be replacing obsolete hardware, improving reliability, correcting batching or weighing issues, adding production reporting, simplifying operation or reducing dependence on knowledge held by one experienced operator. Clearly identifying the primary objectives helps determine which equipment should be replaced and which equipment can remain.
Step 3. Detail the plan.
You want to develop a detailed implementation and commissioning plan. That plan should address panel fabrication, software development, equipment interfaces, testing, installation, shutdown duration, startup support, operator training and updated documentation. It should also identify contingency measures in case an unknown field condition is discovered during installation. In other words: prepare the team, the timeline and the budget for surprises. A successful upgrade depends as much on the cutover and startup plan as it does on the hardware selected.
Step 4. Plan Your Downtime.
The most common concern when upgrading any controls system is production downtime. We all know asphalt plants operate within a limited paving season, and owners may be reluctant to make a major control change when an extended startup problem could affect production commitments.
Here’s something to be wary of: Parts availability can sometimes delay an owner’s decision to upgrade. If replacement relays or PLC component hardware can still be found through secondary-market suppliers or online marketplaces, many plants will continue operating with the existing system. That approach can extend the useful life of the controls, but it also creates increasing uncertainty around component condition, availability and technical support. Eventually, a critical failure may force the plant into an emergency upgrade during the paving season rather than allowing the work to be scheduled and completed during a more opportune shutdown.
Operator familiarity is another consideration to make. Experienced operators may know every characteristic and workaround associated with the existing system. Their knowledge should be incorporated into the design of the new system rather than discarded. Involving operators early generally results in better screen layouts, alarm information, operating sequences and training. But remember that note mentioned in step two: one of your objectives may be to limit your dependence on one person having institutional knowledge. You want to share that knowledge and help all personnel grow as your production grows.
The highest-priority upgrade and most important objective will vary from plant to plant. For example, a system with obsolete controls but accurate scales will have different needs than the plant that has a supportable PLC but unreliable weighing equipment. If you start with the field assessment, you’re starting at the right point. Document what you have, determine your objectives, detail your plan and determine the best time to put the plan in motion. Before you know it, your HMA batch plant’s controls will be up to date and matching your growth.
Mike Raasch is the controls engineer at WEM Automation, Pewaukee, Wisconsin. For more information, contact him at mraasch@wemautomation.com.